Great work by our lads on site this week!!

Great work by our lads on site this week!! Working together with our valued client Moortown Group Limited to successfully complete a new 36m drainage run underneath ancient woodland in Leeds.

Using our guided auger boring tunnelling sys we installed Naylor DN150 denlok clay drainage pipe to straight line and grade, working from a
2.4m manhole shaft, this work was completed in 4days.

If you are intrested and want more information on the various trenchless services TSL offer or want more information on this naylor clay pipe we also supply contact Simon Marsh 07840 848 980

 